After long months of waiting due to the Covid-19 pandemic, it became essential to realize these 6 projects in Casamance, Senegal, in order to support the local population. Indeed, the majority of the projects concerned the power supply of health posts.

In Adéane, a town of 9,000 inhabitants near Ziguinchor, the 5625 Wh installation with 15 PVs of 375 Wp now supplies the health post, but also the reception, the pharmacy, the laboratory and the accommodation for the staff on duty, and provides the electricity needed to operate the lighting as well as some medical equipment and a fridge for storing vaccines and medicines.

  

In the surrounding villages of Tambacoumba and Banghagha, the two dispensaries have been equipped with photovoltaic installations of respectively 2250 Wh with 6 PV of 375 Wp and 3750 Wh with 10 PV of 375 Wp, allowing to ensure a proximity care of the patients day and night.

Groupe Média Sud and Freddy A. explain everything in this report :

On the other side of the Casamance River, in Bloc Sefa, 15 km from Sedhiou, a 3240 Wh photovoltaic installation with 12 PVs of 270Wp recovered, also equips the health post. The elementary school and the secondary school also benefit from photovoltaic installations of respectively 2720 Wh with 8 new PV of 340 Wh and 4080 Wp with 12 PV of 340 Wp allowing to organize remedial classes in the evening.

In these 2 schools, the wells have also been equipped with solar pumps, each powered by 4 PV of 260Wp recovered, which allows them to ensure basic hygiene but also to rehabilitate the vegetable gardens around these buildings.

All the solar and electrical equipment was purchased from local companies and these 6 projects were carried out by local companies: ARESS, for the solar part and Mané & Frères for the electrical installation in Adéane and neighboring villages, and in Bloc Sefa: Synergie Plus and the NQE hardware store in Ziguinchor.

These different work sites were supervised remotely and almost live, by video and photos, by our volunteer project manager Freddy A. (Thanks Whatsapp and Gmail ?). Faithful to its objectives, Energy Assistance continues to transmit the know-how of its members.

At the beginning of October, our two volunteers Freddy A. and Marcel B. went to Casamance for a short mission of control and commissioning of the installations, warmly welcomed by the local populations.